Information about monthly, day-ahead and within-day transmission capacity product booking time for last quarter of gas year 2020
As the monthly transmission capacity purchase time of the Common zone is approaching, information on the exact date and time of booking is collected.
1. Application submission for monthly standard product booking (EEST time zone, i.e Riga time) [1]:
- From 11.06.2020 07:00 to 30.06.2020 16:00 - available monthly capacity product for July
- From 11.06.2020 07:00 to 31.07.2020 16:00 – available monthly capacity product for August
- From 11.06.2020 07:00 to 31.08.2020 16:00 - available monthly capacity product for September
2. Application submission for day-ahead standard product booking (EEST time zone, i.e Riga time) 2:
- From 17.06.2020 07:00 – daily capacity for all days in July (until 16:00 every gas day D-1)
- From 18.07.2020 07:00 – daily capacity for all days in August (until 16:00 every gas day D-1)
- From 18.08.2020 07:00 – daily capacity for all days in September (until 16:00 every gas day D-1)
3. Application submission for within-day standard product booking (EEST time zone, i.e Riga time) 3:
- For every gas day D from D-1 17:00 until D 04:00.
In case of questions, please write to [email protected] or call to +371 25630000
[1] Approved by Public Utilities Commission on April 23, 2020, Common Regulations for the Natural Gas Balancing of Transmission System, sub-clause 4.7.5.1. “b”
2 Approved by Public Utilities Commission on April 23, 2020, Common Regulations for the Natural Gas Balancing of Transmission System, sub-clause 4.7.5.1. “c”
3 Approved by Public Utilities Commission on April 23, 2020, Common Regulations for the Natural Gas Balancing of Transmission System, sub-clause 4.7.5.1. “d”